Your sprint plan assumes 10 days × N people. Your calendar disagrees.

Name where your team sits and the window you’re planning. This subtracts the public holidays each country actually observes and the time off you’ve booked — then shows the working days and person-days that are left, and whether what you’ve committed fits inside them.

Step 1 — the real-capacity audit

Who is in the window, and where

Whole people. Part-time arrangements go in the time-off field, in person-days.

Working week

8 people over 92 days

The real capacity

Thu 1 Jul – Thu 30 Sep

2%

less capacity in this window than the plan assumes

520 person-days, not 528. 66 working days on a Mon–Fri week × 8 people is where the 528 comes from.

What the plan assumes

66 working days × 8 people

528 person-days

Public holidays

1 date landing on a working day

−8

Booked time off

the person-days you entered, across the whole window

0

Actually available

the number a commitment should be sized against

520 person-days

Which days, and for whom

  • Tue 7 Sep8 of 8 off
    Brazil · Independência do Brasil

Only holidays landing on a working day are listed. Where a country moves one that falls on a weekend onto a weekday, the moved date is what appears, marked observed; where it does not, the holiday costs the window nothing and is left out.

What the holiday dates exclude

Coverage is national. Regional, state, municipal and religious holidays are not in these numbers, and neither are company shutdown days or collective-agreement days off unless the note below says otherwise. Every date is computed from a rule rather than fetched, so it holds for any year — but a rule cannot know about a one-off national holiday declared for a royal jubilee or a funeral.

Brazil
Statutory national holidays only; state and municipal holidays are excluded. Carnival Monday and Tuesday, Ash Wednesday and Corpus Christi are federally optional days (ponto facultativo) rather than statutory holidays and are not counted, though many workplaces close for Carnival — so read this set as a floor. Black Consciousness Day counts from 2024, when it became national. Brazil has no weekend substitution.

Step 2 — the commitment check

Against 520 available person-days rather than the 528 the plan assumed. Turning those into points needs a points-per-day pace, and the only honest source for one is your own last few sprints — without them, this shows the person-days and stops there.

Points completed in your last sprints

Optional, and the only thing here that can come from your own history. With 2 or more, the pace below is measured from these. With fewer, it falls back to a default and says so.

Enter the points committed.

What this can and cannot see

Holiday dates are computed from rules rather than fetched from a list, so they hold for any year — but coverage is national only, and each country’s exclusions are spelled out beside the result. The commitment check is arithmetic on the numbers you enter plus the sprint totals you give us. No cross-team benchmark stands behind it, because none exists: nobody can tell you how often commitments like yours land elsewhere, and a number that claimed to would be invented.

Nothing you type here is stored. The whole read is encoded in the URL, which is also how you share it.

Want the same correction applied continuously, with your team’s own calendar and estimates behind it? That’s Ambera Forge · Read what AI-written code costs your team in review

Team capacity calculator: working days after public holidays — Ambera Forge