Your sprint plan assumes 10 days × N people. Your calendar disagrees.

Name where your team sits and the window you’re planning. This subtracts the public holidays each country actually observes and the time off you’ve booked — then shows the working days and person-days that are left, and whether what you’ve committed fits inside them.

Step 1 — the real-capacity audit

Who is in the window, and where

Whole people. Part-time arrangements go in the time-off field, in person-days.

Working week

8 people over 90 days

The real capacity

Fri 1 Jan – Wed 31 Mar

3%

less capacity in this window than the plan assumes

496 person-days, not 512. 64 working days on a Mon–Fri week × 8 people is where the 512 comes from.

What the plan assumes

64 working days × 8 people

512 person-days

Public holidays

3 dates landing on a working day

−16

Booked time off

the person-days you entered, across the whole window

0

Actually available

the number a commitment should be sized against

496 person-days

Which days, and for whom

  • Fri 1 Jan8 of 8 off
    France · Jour de l'anPortugal · Ano Novo
  • Fri 26 Mar4 of 8 off
    Portugal · Sexta-feira Santa
  • Mon 29 Mar4 of 8 off
    France · Lundi de Pâques

2 of these dates take out part of the team only — the window carries days where some of the team is off and the rest is working.

Only holidays landing on a working day are listed. Where a country moves one that falls on a weekend onto a weekday, the moved date is what appears, marked observed; where it does not, the holiday costs the window nothing and is left out.

What the holiday dates exclude

Coverage is national. Regional, state, municipal and religious holidays are not in these numbers, and neither are company shutdown days or collective-agreement days off unless the note below says otherwise. Every date is computed from a rule rather than fetched, so it holds for any year — but a rule cannot know about a one-off national holiday declared for a royal jubilee or a funeral.

France
Mainland national holidays only. Alsace-Moselle additionally has Good Friday and 26 December, and the overseas departments have their own abolition-of-slavery days — all excluded. Whit Monday is worked in some organisations as the journée de solidarité. France has no weekend substitution.
Portugal
Mandatory national holidays only. Municipal holidays (Lisbon 13 June, Porto 24 June) and the Azores and Madeira regional days are excluded, and Carnival Tuesday is granted by annual government decision rather than statute so it is not counted, though most workplaces close. Easter Sunday is omitted; it never falls on a working day. Portugal has no weekend substitution.

Step 2 — the commitment check

Against 496 available person-days rather than the 512 the plan assumed. Turning those into points needs a points-per-day pace, and the only honest source for one is your own last few sprints — without them, this shows the person-days and stops there.

Points completed in your last sprints

Optional, and the only thing here that can come from your own history. With 2 or more, the pace below is measured from these. With fewer, it falls back to a default and says so.

Enter the points committed.

What this can and cannot see

Holiday dates are computed from rules rather than fetched from a list, so they hold for any year — but coverage is national only, and each country’s exclusions are spelled out beside the result. The commitment check is arithmetic on the numbers you enter plus the sprint totals you give us. No cross-team benchmark stands behind it, because none exists: nobody can tell you how often commitments like yours land elsewhere, and a number that claimed to would be invented.

Nothing you type here is stored. The whole read is encoded in the URL, which is also how you share it.