Real-capacity audit

Germany and Spain: real team capacity in Q1 2027

Q1 2027 runs Jan 1 – Mar 31, 2027 and holds 64 working days, Monday to Friday. A plan that says “64 days × 8 people” is claiming 512 person-days. Public holidays take 24 of them back before anyone books a day off — 5% less than the plan assumes.

64

Working days

Monday to Friday in the quarter.

512

Plan assumes

Person-days at 8 people, everyone present.

24

Lost to holidays

Person-days already gone, before any time off.

5%

Shrinkage

Holidays only. Time off and part-time add to this.

This is the half we can compute. The other half is yours.

Holidays come from national rules, so they can be worked out for any window. Booked time off, part-time arrangements and what you have actually committed cannot. Put those in and the same audit says whether the commitment sits inside what is left — using your own recent sprints for pace, with no cross-team benchmark behind it.

Run the audit on your real team

6 holidays land on a working day

Observed dates, sorted. A row marked observed was moved off a weekend by that country’s substitution rule, so the date shown is the day actually taken.

DateHolidayWho is offPeople off
Fri Jan 1NeujahrstagGermany4
Fri Jan 1Año NuevoSpain4
Wed Jan 6Epifanía del SeñorSpain4
Fri Mar 26KarfreitagGermany4
Fri Mar 26Viernes SantoSpain4
Mon Mar 29OstermontagGermany4

This is the read a single org-wide holiday calendar cannot give you. Each date removes only the people in that country, so a Germany/Spain team loses a fraction of a day where a one-calendar model would remove the whole team.

Per country, and what each list excludes

Germany

4 people · 3 days off each · 12 person-days

The nine nationwide holidays only. Many German holidays are set per Bundesland — Epiphany, Corpus Christi, Assumption, Reformation Day, All Saints and Repentance Day among them — so a Bavarian or Saxon team loses more days than this shows. Germany has no weekend substitution: a holiday falling on a Saturday or Sunday is simply lost.

Spain

4 people · 3 days off each · 12 person-days

Nationwide holidays only. Regional and municipal fiestas are excluded, as is Maundy Thursday (a holiday everywhere except Catalonia and Valencia), so every Spanish worker gets local days not listed here. A nationwide holiday falling on a Sunday transfers to the immediately following Monday, as the Estatuto de los Trabajadores requires; one falling on a Saturday is lost.

What this number cannot see

  • Time off is not in it. Booked vacation is not derivable from a rule set, so the shrinkage above is a floor. What your team has actually booked only your team knows, and the calculator is where it enters the number.
  • Everyone is counted full-time. A four-day week or a 60% arrangement removes more again; the calculator takes those as person-days in its time-off field.
  • Only holidays landing on a working day are listed. Nothing in this window was left out for landing on a weekend. This is why the list here can be shorter than an official calendar.
  • Substitution rules differ per country. The UK, Ireland and Canada move a weekend holiday to the next free weekday, US federal practice observes a Saturday holiday on the Friday before, and Spain transfers a Sunday holiday to the following Monday. Most of continental Europe simply loses the day, and a compensating day granted by an employer has no fixed date to compute.
  • Regional, state, municipal and religious holidays are excluded. Each country’s own caveat above says what that leaves out for it. It matters most in Germany, Spain, Canada and the United Kingdom, where a large share of real days off are set below the national level.

The full method, including what the commitment check does and does not rest on, is on the methodology page.

Your window, your team

This page assumes 8 people split evenly across the two countries and no time off, because that is all a public rule set can know. The calculator opens on this window and this team — change the dates, add your booked days and your commitment, and the same arithmetic runs on your real numbers.

Run the real-capacity audit

Each country on its own