Real-capacity audit

Czechia: real team capacity in Q4 2027

Q4 2027 runs Oct 1 – Dec 31, 2027 and holds 66 working days, Monday to Friday. A plan that says “66 days × 8 people” is claiming 528 person-days. Public holidays take 24 of them back before anyone books a day off — 5% less than the plan assumes.

66

Working days

Monday to Friday in the quarter.

528

Plan assumes

Person-days at 8 people, everyone present.

24

Lost to holidays

Person-days already gone, before any time off.

5%

Shrinkage

Holidays only. Time off and part-time add to this.

This is the half we can compute. The other half is yours.

Holidays come from national rules, so they can be worked out for any window. Booked time off, part-time arrangements and what you have actually committed cannot. Put those in and the same audit says whether the commitment sits inside what is left — using your own recent sprints for pace, with no cross-team benchmark behind it.

Run the audit on your real team

3 holidays land on a working day

Observed dates, sorted. A row marked observed was moved off a weekend by that country’s substitution rule, so the date shown is the day actually taken.

DateHolidayPeople off
Thu Oct 28Den vzniku samostatného československého státu8
Wed Nov 17Den boje za svobodu a demokracii8
Fri Dec 24Štědrý den8

What the national list for Czechia leaves out

Czechia

8 people · 3 days off each · 24 person-days

Czechia has no regional public holidays and no weekend substitution, so the national set above is the whole statutory story.

What this number cannot see

  • Time off is not in it. Booked vacation is not derivable from a rule set, so the shrinkage above is a floor. What your team has actually booked only your team knows, and the calculator is where it enters the number.
  • Everyone is counted full-time. A four-day week or a 60% arrangement removes more again; the calculator takes those as person-days in its time-off field.
  • Only holidays landing on a working day are listed. 2 national holidays in this window fall on a Saturday or Sunday and are left out — they cost a Monday-to-Friday team nothing. This is why the list here can be shorter than an official calendar.
  • Substitution rules differ per country. The UK, Ireland and Canada move a weekend holiday to the next free weekday, US federal practice observes a Saturday holiday on the Friday before, and Spain transfers a Sunday holiday to the following Monday. Most of continental Europe simply loses the day, and a compensating day granted by an employer has no fixed date to compute.
  • Regional, state, municipal and religious holidays are excluded. Each country’s own caveat above says what that leaves out for it. It matters most in Germany, Spain, Canada and the United Kingdom, where a large share of real days off are set below the national level.

The full method, including what the commitment check does and does not rest on, is on the methodology page.

Your window, your team

This page assumes 8 people and no time off, because that is all a public rule set can know. The calculator opens on this window and this team — change the dates, add your booked days and your commitment, and the same arithmetic runs on your real numbers.

Run the real-capacity audit

Distributed pairings